Exhibit 10.30
Capstone Engineered Solutions Corporation
27812 Pollensa
M ission Viejo, CA 92692 US
jdcrouse@m e.com
Estimate
ADDRESS
Capstone Green Energy Corporation
16640 Stagg St
Van Nuys, CA 91406
ESTIMATE 1002
DATE 04/26/2022
EXPIRATION DATE 05/15/2022
DATE | SERVICE | DESCRIPTION | QTY | RATE | AMOUNT |
04/26/2022 | Rental System Installation | Travel and Per Diem | 1 | 5,500.00 | 5,500.00 |
04/27/2022 | Rental System Installation | Receive and set units in place, install air inlet hoods and shipped loose hardware | 3 | 2,500.00 | 7,500.00 |
04/29/2022 | Rental System Installation | Supply and install HDPE gas piping and shutoff valves for each C1000 and blind flange for expansion | 1 | 62,500.00 | 62,500.00 |
04/29/2022 | Rental System Installation | Install CGE supplied power cables and cable tray to each C1000 and mining box. Installation hardware supplied by CESC | 1 | 49,530.00 | 49,530.00 |
05/03/2022 | Rental System Installation | Install CGE supplied gas filter and regulator skid | 1 | 5,275.00 | 5,275.00 |
05/03/2022 | Rental System Installation | Supply and install control cable conduits to each C1000 | 1 | 16,800.00 | 16,800.00 |
05/04/2022 | Rental System Installation | Install CGE supplied PC for remote communications | 1 | 3,450.00 | 3,450.00 |
05/05/2022 | Rental System Installation | Modify C1000 for flatpac control scheme, program unit Unit #1 C1K control for master operation | 1 | 5,420.00 | 5,420.00 |
05/06/2022 | Rental System Installation | Commission units for 3MW standalone operation | 1 | 4,500.00 | 4,500.00 |
$20,000.00 Deposit to start
Balance due at com pletion
TOTAL $160,475.00