Description | Units | Open pit | Underground | ||||||||
Gold price | US$/oz | 1,800 | 1,800 | ||||||||
Copper price | US$/lb | 3.50 | 3.50 | ||||||||
Mining cost | US$/t processed | 4.10 | 19.50 | ||||||||
Process cost | US$/t processed | 8.48 | 8.48 | ||||||||
Filter plant cost | US$/t processed | 2.13 | 2.13 | ||||||||
IEWMF and water management | US$/t processed | 0.13 | 0.13 | ||||||||
G&A | US$/t processed | 2.78 | 2.78 | ||||||||
Overall costs | US$/t processed | 17.62 | 33.02 | ||||||||
Mill Au recovery | % | 86.7 | 86.7 | ||||||||
Mill Cu recovery | % | 91.5 | 91.5 | ||||||||
Cut-off used | AuEq g/t | 0.3 | 0.7 |
40-F
2023 FY
EGO
Eldorado Gold Corp.
28 Mar 24
Annual report (Canada)
2:02pm
Table 1-5: Operating Costs
Cost Centre | Production years total cost (US$ M) | Production years cost per tonne of production ore (US$/t) | ||||||
Open pit mining | 245 | 4.24* | ||||||
Underground mining | 1,681 | 19.32* | ||||||
Process plant | 1,247 | 8.54 | ||||||
Tailings filtration plant | 314 | 2.15 | ||||||
Backfill plant | 28 | 0.19 | ||||||
Water system | 20 | 0.14 | ||||||
G&A | 409 | 2.80 | ||||||
Subtotal mining | 1,925 | 13.18 | ||||||
Subtotal non-mining | 2,018 | 13.81 | ||||||
Total | 3,944 | 26.99 |